Friday, December 10, 2010

CS615 Mid Term Current Paper (Dec 2010)

CS615 Mid Term Current Paper (Dec 2010)

1. Describe the concept of information description (2)
2. write the steps of product evaluation (2)
3.write 6 methods of requirement elicition. (3)
4. execution process tasks(3)
5. What is the difference between interim version and baseline versions (5)
6. What is the difference between data gathering data usage guidlines (5)


Project management processes can be organized into _____________ groups 
► Four
► Five
► Six
► Seven

Finally, the specification includes a ________ 
► Bibliography
► Appendix
► Both Bibliography and Appendix
► Reference 
Requirements are refined and analyzed to assess their clarity, completeness, and_______ 
► Correctness
► Consistency
► Concurrency
► None of given
A software project that meets all the stated objectives is a success of _________ 

► Project quality
► Project fundamental purpose 
► Project management myth
► Project requirement

Another Paper:

1. Quality Fuction Deployment (5)
2. Formal Technical Review (5)
3. Configuration Control Tools(2)
4. Attributes of Software Design (2)
5. SQA activities. (3)