Tuesday, February 15, 2011

Mgt613 Final Term Current Paper (Feb 2011)

Mgt613 Final Term Current Paper (Feb 2011)

Total Questions 69
MCQ's 62
Short Question 07

Time 120 min
MCQ's were conceptual

Short Question were as under

Q.1: 'Demand for service is usually difficult to predict'
Comment on this statement in the light of aggregate planning ( 3 marks)

Q.2: How is inventory storage minimized in JIT system ( 3 marks )

Q.3: As a operational manager of ABC company, what do you think are the various measures that lead to good scheduling result ( 3 marks )

Q.4: Find maximin, maximax and lapalace

small 10000 8000
medium 12000 20000
large 18000 15000 ( 5 marks)

Q.5: Comment on the statement: 'Use of over time /slake time is less severe method for changing capacity then hiring and laying of workers' ( 5 marks )

Q.6: Consistent high quality of JIT is main focus of JIT. How JIT aim at predicting 'Quality at Source' ( 5 marks )

Q.7: Senior managment of a service firm has initiated a short term project of building a new facility of a designated area. What will be the responsibilities and qualification of a project manager regarding this project ( 5 marks)

0 comments:

Post a Comment